Services - Estimating and Cost
Control
Callahan, Inc. will maintain an open
book approach on this CM project. This approach allows the owner to
review all project information and provides assurance that the project
team is always working in the best interest of the owner.
Callahan, Inc. cost control process
is set up and based on the owner and the architect's acceptance and
approval of the project budget. The project budget will be submitted
in complete detail and all items of the budget, will be reviewed by
the owner and the project team. Once the budget has been approved,
it will be transferred into a control estimate or GMP.
As design progresses we review proposed
design elements and changes and confirm that the design intent reflects
what was included in the project control budget. If the design is
impacting the control budget, Callahan, Inc. immediately informs the
owner and project team of potential problems. We update the project
budget on an as needed or monthly basis unless costs and design remain
constant or unchanged. Callahan, Inc. always maintains the control
budget and records past budgets so a history is established. These
reports are detailed to include design status, the release of bid
packages, actual subcontractor buyouts, changes, and design changes.
This history allows the project team to review project budgets and
costs as the project progresses.
Subcontracting
Callahan, Inc. would review with the
owner a proposed subcontractor list prepared by our staff for review
and discussion. Our intent is to finalize a list of all qualified/approved
subcontractors with input from the Project Team in order to prepare
to fast track the bidding award process.
In pre-qualifying subcontractors and
vendors, we will ensure that all prospective bidders:
- Have a previous working relationship
or track record with either Callahan, Inc. or the owner, or have
been highly recommended and have met all of our prequalification
requirements.
- Have the financial capability to
perform the work.
- Have references and experience in
projects of a similar size or larger.
- Have proper insurance coverage.
- Have adequate administrative and
trade workforce to provide a quality product within the schedule
time frame.
Purchasing
After Callahan, Inc. has established
a priority list based on the status of the contract drawings, project
schedule and anticipated lead times of specific equipment and materials,
we will develop a purchasing strategy for competitive bidding of the
major material purchases and all subcontracts.
Callahan, Inc. will prepare the appropriate
bid packages / RFPs to include bidding requirements, work scope, bid
breakdown requirements, labor rates and any other items that may be
beneficial to controlling the cost of all work as the project progresses.
Once a bid package / RFP has been assembled,
reviewed and approved by all the team members, Callahan, Inc. will
schedule a subcontractor pre-bid meeting to make sure all bidders
are totally informed of the requirements of the project. Work scope
will be addressed, along with quality standards, safety requirements,
insurance requirements, schedule, billing and requisitioning requirements,
and all other issues on which a successful project depends.
Once bids are received, they will be
reviewed, descoped and tabulated. We will prepare a bid analysis spreadsheet
for review by the owner and the architect/engineer team for final
selection and award.
Subcontractor agreements will include
all the provisions of the contract documents. Subcontract awards or
material purchases will not occur without the approval of the owner.
Each subcontractor must have a fully executed subcontract agreement
and approved insurance certificate in our files prior to access to
the jobsite and the start of their work.